This letter is to inform you of work to resurface the M65 between junctions 8 and 10. In total, we plan to resurface over 40km of carriageway. The work will take place on both sides of the carriageway and will include the replacement of road markings, bridge joints and traffic detection cables. The purpose of our work is to ensure we keep the network safe and operational, as well as improving journeys for our customers. 

Work is due to start on or shortly after 18 October 2021 for around 17 weeks. This will take place Monday to Friday, between the hours of 8pm and 5am (extended to 7am during the weekend).

For safety, overnight full carriageway closures are required on the M65 between junctions 8 and 10. These will be in place in many phases, and only one side of the carriageway will be closed at a time. Occasionally, we will need some closures at junction 7 and 11 to tie in the surfacing work. Associated slip road closures are also required, and to ensure journeys are maintained localised signed diversion routes will be in place.

Whilst we always aim to work to our schedule, unforeseen circumstances such as severe weather conditions may mean slight changes occur at short notice. Every effort will be made to ensure disruption is kept to a minimum. However, these works will inevitably generate some noise and disruption and we’d like to apologise in advance for any disturbance. 

How to find out more
For more information on this and other work in the north-west, please visit https://highwaysengland.co.uk/regions/north-west. You can also follow us on twitter @HighwaysNWEST.

If you have any queries about the work, please contact us on 0300 123 5000. Or you can email us on [email protected].

Yours faithfully, 

Rob Williams

Rob Williams, Programme Delivery Manager